When task time measurements are not reported by developers
Measurements of the time taken to complete a software development task usually rely on the values reported by the person doing the work. People often give round number answers to numeric questions. This rounding has the effect of shifting start/stop/duration times to 5/10/15/20/30/45/60 minute boundaries.
To what extent do developers actually start/stop tasks on round number time boundaries, or aim to work for a particular duration?
The ABB Dev Interaction Data contains 7,812,872 interactions (e.g., clicking an icon) with Visual Studio by 144 professional developers performing an estimated 27,000 tasks over about 28,000 hours. The interaction start/stop times were obtained from the IDE to a 1-second resolution.
Completing a task in Visual Studio involves multiple interactions, and the task start/end times need to be extracted from each developer’s sequence of interactions. Looking at the data, rows containing the File.Exit message look like they are a reliable task-end delimiter (subsequent interactions usually happen many minutes after this message), with the next task for the corresponding developer starting with the next row of data.
Unfortunately, the time between two successive interactions is sometimes so long that it looks as if a task has ended without a File.Exit message being recorded. Plotting the number of occurrences of time-gaps between interactions (in minutes) suggests that it’s probably reasonable to treat anything longer than a 10-minute gap as the end of a task.
The plot below shows the number of tasks having a given duration, based on File.Exit, or using an 11-minute gap between interactions (blue/green) to indicate end-of-task, or a 20-minute gap (red; code+data):

The very prominent spikes in task counts at round numbers, seen in human reported times, are not present. The pattern of behavior is the same for both 11/20-minute gaps. I have no idea why there is a discontinuity at 10 minutes.
A development task is likely to involve multiple VS tasks. Is the duration of multiple VS tasks more likely to sum to a round number than a nonround number? There is no obvious reason why they should.
Is work on a VS task more likely to start/end at a round number time than a nonround number time?
Brief tasks are likely to be performed in the moment, i.e., without regard to clock time. Perhaps developers pay attention to clock time when tasks are expected to take some time.
The plot below shows the number of tasks taking at least 10-minutes that are started at a given number of minutes past the hour (blue/green), with red pluses showing 5-minute intervals (code+data):

No spikes in the count of tasks at round number start times (no spikes in the end times either; code+data).
Why spend time looking for round numbers where they are not expected to occur? Publishing negative results is extremely difficult, and so academics are unlikely to be interested in doing this analysis (not that software engineering researchers have shown any interest in round number usage).